MW GOLDEN CONSTRUCTORS is preparing to commence HVAC renovations for Side Creek Elementary, an Auror
MW GOLDEN CONSTRUCTORS will furnish and install new mechanical roof top units after an extensive demolition of five (5) existing penthouse structures. Side Creek Elementary will be upgraded with DDC controls, thermostats and VAVs. In order to energize the new mechanical equipment, a new and larger transformer will be installed including secondary service and switchboard. MWGC will renovate the building entrance including new storefront, entrance, metal soffit and wall panels,